Published in United States

US Utility PPL Reports 23% Increase in Data Center Pipeline, Reaching 25.2GW.

Feb 23, 2026 | Posted by Abdul-Rahman Oladimeji

In its latest earnings report, the utility said that it now expects at least 10GW of data center load to be signed under Electricity Service Agreements (ESA) by the end of Q1. Vincent Sorgi, president of PPL, said during the call that he believes “ all of the 25.2GW of projects have a high probability of completion.”

Sorgi also said that all of the ESAs “include strong customer protections, such as prepayments and credit support, as well as minimum load requirements for data center customers to pay approximately 80 percent of forecasted load until the costs incurred to extend service are fully recovered.”

During the earnings call, the utility also referenced concerns about long-term affordability for ratepayers across the PJM Interconnection market, which has seen rising prices tied to data center growth.

“With the scale of data center growth we are seeing, we absolutely need to build new reliable generation to meet that demand,” said Sorgi. “The recent call by  President Trump and the state governors in PJM for an emergency auction to spur construction of generation, that is a clear acknowledgment of what we have been saying for years.”

The utility said that if the auction were to come to fruition, it could produce around 6-7GW of new power generation. However, Sorgi said that this “would not address the expected data center demand in PPL Electric’s service territory, let alone data center demand across all of PJM. What the auction does signal, however, is increased pressure on data centers to bring their own generation to market or at least pay for the new generation required to power their data centers.”

There are 4701 data centers in United States.

Sitemap for Peterson Companies' Leesburg Gateway Project
Posted in Peterson: Leesburg Gateway Campus Source: Peterson Companies
Posted in Stonebridge: Fort Meade Campus |
Tentative site plan for Zydeco Development's data center in Hutto, Texas
Posted in Zydeco Development: Hutto, Texas Source: Zydeco
Proposed site for IND A1 data center in Indianapolis
Posted in Metrobloks: Indianapolis A1 Source: Metrobloks
Posted in DataBank: Los Angeles |
Posted in Edged: Phoenix |
The Autophone of Laredo data center in Texas (Image 5)
Posted in Autophone: Laredo Source: Autophone of Laredo
The Autophone of Laredo data center Texas (Image 4)
Posted in Autophone: Laredo Source: Autophone of Laredo
The Autophone of Laredo data center Texas (Image 3)
Posted in Autophone: Laredo Source: Autophone of Laredo
The Autophone of Laredo data center in Texas (Image 2)
Posted in Autophone: Laredo Source: Autophone of Laredo
The Autophone of Laredo data center in Texas (Image 1)
Posted in Autophone: Laredo Source: Autophone of Laredo
Posted in Google: Project Cannoli |
Site Aerial Map
Posted in Grandilla: Phoenix, Arizona Source: https://mccobagenda.databankcloud.com/AgendaOnline/Documents/DownloadFileBytes/02.03%20CPA250009%20Z250027%20BOS%20REPORT.PDF.pdf?documentType=1&meetingId=4622&itemId=264342&publishId=145477&isSection=False&isAttachment=True
Meta: Project Domino
Posted in Meta: Project Domino Source: https://www.datacenterdynamics.com/en/news/meta-announces-1gw-data-center-campus-in-indiana/
Sequitor Edge Data Center
Posted in Sequitor Edge: Rapid City, South Dakota Source: https://sequitoredge.com/news/sequitor-edge-data-center-coming-to-rapid-city/
Proposed site for Wildwood Ranch AI Campus in Joplin, Missouri
Posted in Wildwood Ranch: Joplin, MO Source: Joplin City Council
Proposed site for Takanock's Project Baccara in Arizona
Posted in Takanock: Project Baccara Source: Takanock
Proposed sitemap for Project Laurel in Limerick Township
Posted in Project Laurel Source: Limerick Township | MCD 7 LLC
Proposed site plan for Project Flex in Lyon Township, Michigan
Posted in Verrus: Project Flex Source: Verrus
Proposed siteplan for Project Delta in Stokes County
Posted in Project Delta Source: Project Delta
EdgeConneX acquired a 180-acre parcel near AUS01 in Bastrop, Texas.
Posted in EdgeConneX: Austin AUS01 Source: Bastrop CAD
Preliminary siteplan for Cloverleaf's data center in St. Louis, Missouri
Posted in Cloverleaf: Troy Campus Source: Cloverleaf Infrastructure
Proposed site for Morris Technology Park
Posted in Tract: Morris Tech Park Source: Tract
Proposed layouts of the Janesville data center
Posted in APECS Data Center Campus Source: Planning documents
Site for QumulusAI's data center in Denton, TX
Posted in QumulusAI: Denton, TX |
Hut 8 launched Project Vega in Texas
Posted in Hut 8: Project Vega Source: Hut 8